institutions for these hedging transactions. Our maximum credit risk loss with these institutions is limited to any gain on our outstanding contracts. As of December 31, 2012, December 31, 2011 and June 30, 2013, these currency forward contracts had net notional amounts of $169.3 million, $96.4 million and $173.9 million, respectively, and are accounted for as economic hedges, for which hedge accounting was not applied.

11. COMMITMENTS AND CONTINGENCIES

Operating Leases and Purchase Obligations

We lease buildings, equipment and automobiles under operating leases. Rental expense was $4.6 million and $2.1 million for the years ended December 31, 2012 and 2011, respectively. The total future commitments under operating leases as of December 31, 2012 were $22.3 million, of which $21.6 million is noncancellable. Our operating lease obligations as of December 31, 2012 were as follows:

 

     Payments Due By Period  
     Total      2013      2014      2015      2016      2017      Thereafter  
In millions                                                 

Operating leases

   $     22.3        $     5.8        $     4.9        $     4.7        $     3.5        $     1.6        $     1.8   

Purchase Commitments

As part of our restructuring activities announced in the fourth quarter of 2011, we provided notice to several of our vendors with whom we had long-term supply contracts that we will no longer be fulfilling our purchase obligations under those contracts. In connection with the restructuring, we recorded significant restructuring liabilities associated with the estimated settlements arising from these actions based on management’s best estimates of the ultimate outcome of these contract resolutions at that time. As of December 31, 2012, and June 30, 2013, we have recorded total liabilities of $69.5 million and $29.7 million, respectively, associated with the settlements arising from these take-or-pay supply agreements and estimated purchase obligations, all recorded as short-term restructuring liabilities in the combined balance sheet. These amounts include purchase obligations as well as two settlement agreements with Evonik. See Note 3 for additional information regarding the two settlement agreements. The amount of purchase obligations accrued as of December 31, 2012 and June 30, 2013 represents our best estimate of the probable amounts to settle all of our obligations based on presently known information, which involve the use of assumptions requiring significant judgment. These estimates include the contractual terms of the agreements, including whether or not there are fixed volumes and/or fixed prices. In addition, under certain contracts, the counterparty may have a contractual obligation to sell the materials to mitigate their losses. We also included in our estimate of losses consideration around whether we believe the obligation will be settled through arbitration, litigation or commercially viable alternative resolutions or settlements. We intend to vigorously defend ourselves against any arbitration or litigation. Due to the inherent uncertainties of arbitration and litigation, we cannot predict the ultimate outcome or resolution of such actions. The actual amounts ultimately settled with these vendors could vary significantly, which could have a material adverse impact on our business, results of operations and financial condition.

Indemnification

We have agreed to indemnify some of our semiconductor customers against claims of infringement of the intellectual property rights of others in our sales contracts with these customers. Historically, we have not paid any claims under these indemnification obligations, and we do not have any pending indemnification claims as of December 31, 2012, December 31, 2011 and June 30, 2013.

Legal Proceedings

We are involved in various legal proceedings, claims, investigations and other legal matters which arise in the ordinary course of business. Although it is not possible to predict the outcome of these matters, we believe that the ultimate outcome of these proceedings, individually and in the aggregate, will not have a material adverse effect on our financial position, cash flows or results of operations.

 